Green Silicon Carbide Manufacturing JSC’s Development Roadmap
Jul – Dec 2024
Stage 1 - Foundation
Establishment of the company and positioning within the global SiC ecosystem.
Focus on strategic direction, technical feasibility, partner selection, and preparation for industrial scale, including securing a future manufacturing site.
Jan – Dec 2025
Stage 2 - Technology Build-up
Launch of core licensing through early technology partnerships.
Development of initial transistor and advanced module concepts, digital-twin capabilities, and pilot packaging line design.
Initiation of Business plan development with Grant Thornton.
Early market presence through demonstrator products and industry engagement.
Jan – Oct 2026
Stage 3 - Industrial and R&D/Data Centre Readiness
Establishment and operational launch of the R&D/Design Centre.
Qualification of first products, an operational small-scale packaging line, and active engagement with customers and distributors.
Completion of technology transfer, supplier agreements, regulatory readiness, and full preparation for manufacturing kick-off.
Completion of factory Blueprints and ensuring full administrative readiness for construction activities.
Early Marketing supply and availability of the full GSCM product lineup.
Oct 2026- Mar 2027
Stage 4 - Investment Round: Fab Completion & Operations
Mar 2027-2029
Stage 5 - Construction & Commissioning
Construction and fit-out of the manufacturing facility.
Installation of production equipment, recruitment and training of operational teams, and integration of end-to-end manufacturing processes.
2030
Stage 6 - Production Launch
Factory commissioning and ramp-up to commercial production.
First customer deliveries, market entry, and scalable revenue growth.